Norway

The following GO-eligible power plants were commissioned in Norway between January and March 2019:

  • Marker Vindpark 54 MW / 192 GWh p.a.
  • Storelva 8 MW / 23 GWh p.a.
  • Vaksvik 7.74 MW /21 GWh p.a.
  • Skorga 2.9 MW / 10 GWh p.a.
  • Sagelva Kraftverk 2.8 MW / 8.6 GWh p.a.

Combined, the power plants have an installed capacity of 75.44 MW and expected annual production of 254.6 GWh. The Marker wind park brought 54 MW wind capacity to the market. The remaining power plants commissioned during the period brought a to...